Table 2 Optimization of bed management project work streams

From: Optimizing inpatient bed management in a rural community-based hospital: a quality improvement initiative

Work stream deliverable

Timeline

Tactics

Pre-admission processa

January 1 through March 31, 2022

Progressive care unit

Pre-admission process for surgical patients before 12 pm

Transfer planb

January 1 through June 30, 2022

ED lateral transfer process under way

Scripting on capacity and capability for staff

MATC partnership to triage patients to regional sites

EMS assessment

Updated admission guidelinesc

January 1 through June 30, 2022

Criteria outlined to reserve beds for patients with severe illness in 4 strategic service lines

Updated diversion plan

January 1 through June 30, 2022

Diversion service area

Diversion activation

Hospital bed management optimization dashboard

  1. Abbreviations: ED Emergency department, EMS Emergency medical services, MATC Midwest Admission and Transfer Center, PCU Progressive care unit
  2. aPre-admission for surgical procedures planned the night before admission
  3. bRedirection of patients from sites other than Mayo Clinic to regional sites and from the Mayo Clinic Health System hospital in Mankato, Minnesota, to regional sites in the Southwest Minnesota region
  4. cLevel of care and specialty beds