Intervention period | ||||
---|---|---|---|---|
0-6 months | 6-12 months | 12-18 months | 18-24 months | |
N delivered/N planned (%) | N delivered/N planned (%) | N delivered/N planned (%) | N delivered/N planned (%) | |
Group 1 | ||||
Geriatric assessment | 329/364 (90.4) | 227/337 (67.4) | 181/315 (57.5) | 212/304 (69.7) |
Care plan | 318/331 (96.1) | 231/234 (98.7) | 186/198 (93.9) | 168/216 (77.8) |
MTC | 1/10 (10) | 3/10 (30) | 0/10 (0) | 5/10 (50) |
Group 2 | ||||
Geriatric assessment | 157/172 (91.3) | 146/161 (90.7) | 132/158 (80.0) | |
Care plan | 155/157 (98.7) | 130/146 (89.0) | 121/136 (89.0) | |
MTC | 0/9 (0) | 2/9 (22.2) | 2/9 (22.2) | |
Group 3 | ||||
Geriatric assessment | 134/161 (83.2) | 114/155 (73.5) | ||
Care plan | 126/134 (94.0) | 111/118 (94.1) | ||
MTC | 1/8 (12.5) | 4/8 (50) | ||
Group 4 | ||||
Geriatric assessment | 103/129 (79.8) | |||
Care plan | 77/103 (74.8) | |||
MTC | 0/7 (0) |